Roadmap & Phasing

Version Philosophy

ComplianceCheck releases in three phases, each adding capability without breaking prior work. v1 is manually-assisted validation; v2 adds intelligence (anomaly detection); v3 adds workflow automation (signoff routing).

v1.0: Assisted Compliance Checking (Target: Early Q3 2026)

Mission: Prove the core concept — that automated checklist validation + human review = faster, consistent compliance audits.

What ships:

Success criteria:

Known limitations (v2+):

v1.1: UX Polish & Quick Wins (Target: Mid Q3 2026, ~2 weeks post-launch)

Not critical for launch, but high-value if time permits before/after v1 release.

Additions:

v2.0: Intelligent Audit Assistant (Target: Q4 2026 - Q1 2027)

Mission: Add intelligence layer — detect anomalies, inconsistencies, deviations from standards.

Major additions:

Effort estimate: 8-12 weeks

v3.0: Workflow Automation (Target: Q1 - Q2 2027)

Mission: Automate approval routing and signoff tracking — remove manual email/spreadsheet coordination.

Major additions:

Effort estimate: 6-8 weeks

Timeline

PhaseTarget DateDurationBuild Team StatusStatus
Blueprint ReviewNow - Feb 20261-2 weeksChin + Greg feedback, clarify QMS checklistIN PROGRESS
Build Team SelectionFeb 20261 weekIdentify internal or external builder(s)PENDING
v1 DevelopmentFeb - Apr 202610-12 weeksWS-1 through WS-10NOT STARTED
v1 UAT & LaunchEarly Q3 20262-3 weeksUser testing, bug fixes, go-livePENDING
v1.1 Polish (optional)Mid Q3 20262 weeksPost-launch quick winsPENDING
v2 DevelopmentQ4 2026 - Q1 202710-12 weeksAnomaly detection, integrations, recommendationsFUTURE
v3 DevelopmentQ1 - Q2 20278-10 weeksWorkflow automation, SSO, integrationsFUTURE

Milestone Overview

v1.0 Milestones:

Success Metrics by Version

Metricv1 Targetv2 Targetv3 Target
Audit cycle time3-5 days (vs. 2-3 weeks manual)1-2 days (anomaly detection accelerates review)<1 day (automated routing)
Finding accuracy95%+ compliance with checklist98%+ (cross-doc validation)99%+ (with recommendations)
User adoption100% of new projects audited100% of projects + retroactive batch audits100% automation of approval workflow
Cost per audit50% of manual cost25% of manual cost10% of manual cost (automation)
Uptime99%+99.5%+99.9%+ (production-grade)

Critical dependency: v1 timeline depends on build team being selected by late February 2026. If delayed, timeline shifts right.

v2/v3 gates: v2 only proceeds if v1 reaches 95% accuracy and 90% auditor satisfaction. v3 depends on v2 being stable in production.